Our booking system will be unavailable on 25.11.26 from 9:30am to 10:30am due to maintenance. During this time, bookings and amendments cannot be made online, by phone, or at the Ferry Travel Shop. Apologise for any inconvenience.
Our booking system will be unavailable on 25.11.26 from 9:30am to 10:30am due to maintenance. During this time, bookings and amendments cannot be made online, by phone, or at the Ferry Travel Shop. Apologise for any inconvenience.

Progress is being made, and we are pleased to provide a further update on the work currently being carried out aboard Manxman.
As outlined in our previous update, the existing locking arrangement no longer met the fine tolerances required to secure the shaft correctly. We can now confirm that the new tapered locking wedges have arrived at Balaena's Birkenhead shipyard and have been successfully positioned. The next stage of the process will see installation of the port shaft commence.
Representatives from Lloyd's Register are currently on site to oversee the installation work and ensure all requirements are met. In addition, Lloyd's Register's investigation team is scheduled to return on 25 November to continue its ongoing review.
Alongside this work, a number of maintenance activities have been completed elsewhere on board. The vessel's pet deck has received a new deck coating, while general housekeeping and tidying works have also been carried out.
Manxman remains on course to return to service on 11 December, subject to the successful completion of the remaining work, regulatory inspections and sea trials.
All updates on Manxman's progress can be found on our dedicated page: https://www.steam-packet.com/manxman-update
